Important dates and deadlines
Here you find important dates and deadlines. Please check this website regularly for updates.
| March | |
|---|---|
| until mid March 2021 | Finalizing the "Quick start Guides" for each sensor type. |
| 15. March 2021 | Deadline for non-EU shipments: the packing lists must be sent to Tobias: tost@norceresearch.no |
| April | |
| 12. - 14. April 2021 | Test run at the facility: tank insulation, pump test,... |
| 30. April 2021 | Deadline for EU shipments: The packing lists must be sent to Tobias: tost@norceresearch.no |
| June | |
| 07. June 2021 | Deadline for instruments arriving at GEOMAR (non-EU shipments) |
| 15. June 2021 | Deadline for instruments arriving at VLIZ (EU shipments) |
| 16. - 25. June 2021 | Setting up the infrastructure at the Marine station Ostend by the core team |
| 25. - 27. June 2021 | Test run with all instruments running |
| 28. June - 09. July 2021 | Inter-comparison |
| July | |
| 10./11. July 2021 | Dismantle instruments, pack |
| August | |
| 02. August 2021 | Instruments will be shipped back to participants. If this date is too late, please let Tobias know and we arrange differently. |
| August onwards | Preparing and publishing results. |
| Fall 2021 | |
| October/November 2021 | 2-3 day (virtual) meeting to discuss the results and science around it. |